Stalled prime location real estate projects mar HCM City
  • | tienphong, dtinews.vn | June 07, 2017 02:29 PM
The chairman of HCM City Nguyen Thanh Phong has criticised three projects that remain uncompleted after a decade.

The Saigon One Tower, SJC Tower and Lavenue Crown Tower were named and shamed during a meeting between the city's leaders and real estate and construction companies on June 3.

Phong asked the Department of Construction to review all incomplete projects in the city and focus on finishing on-going constructions and rechecking those that haven't even started. According to Phong, many of those projects are located in prime locations.

On June 5, there was no activity at the named projects. Saigon One Tower's construction was started in 2007 and expected to be completed in 2009. It would be HCM City's third highest tower at 195 metres tall with VND5trn (USD220m) investment. However, only 80% was completed in 2011 and the project has stalled.

 

Saigon One Tower's construction was started in 2007

SJC Tower is also located on prime location that can easily access Le Thanh Ton, Nam Ky Khoi Nghia, Nguyen Trung Truc and Le Loi streets. According to the planning, the tower will cost VND2trn (USD88.1m), cover 8,600 square metres with 54 floors. But after being given permit in 2007, the project remains an empty lot.

Lavenue Crown project is right next to Diamond commercial centre and the opposite of the headquarters of District 1 People's Committee. Lavenue Crown is a luxury apartment and hotel complex at 36 floors. Currently, the 4,921-square-metre space is being used as a parking lot.

Le Hoang Chau, chairman of the HCM City Real Estate Association said each project had a specific situation but all of them were started when the real estate market in Vietnam was experiencing a slump. HCM City still has many projects that can't be continued or the investors just want to sit on the land.

Chau said there was a solution for Saigon One Tower so the project could be completed in the coming time. "The difficulty is there are four to five houses that haven't been cleared so the infrastructure isn't very pretty. I haven't received any information about the other two projects," he said.

He went on to say that the authorities need to issue punishments for tardy developments.